Update: Ela Road at Long Grove Road
5/11/2024 - Storm sewer installation is in progress. Next week crews will continue to install storm sewer, followed by patching of the road at the storm sewer crossings. We are scheduled to move into the first traffic stage on Wednesday (5/15), where traffic will be shifted west while storm sewer work and road widening begins on the east side of Ela Rd.
Traffic impacts: Watch for workers, flaggers, and trucks entering and leaving the work area, be alert for the new traffic pattern.
Motorists are urged to drive carefully, be aware of the new traffic pattern, flaggers working, and of trucks entering and exiting the job site. Learn more